Work Profile Report : 39W70

मा0मु0मत्री घोषणा (2008-09 में) सिद्धसौड-टाट-पाली-सिमली मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा.सं. 4199/111-2/08 (मु0मं0घो0/08 दिनांक 24.12.08

TS Amount (lakhs) : 110.25 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

110.25

Resanction Cost :

110.25

Tentative Cost :

110.25

Exp. Upto Last Fy :

81.70

For CFY 2025-2026

Remaining :

28.55

Demand :

20.00

Allotment :

23.06

Exp in CFY :

23.06

Total Up to Date Exp :

104.77

Work completed

Sanction on : 17 years 1 month ago

24 Dec 2008

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

100 %

Tentative Completion date on : 2 months 1 day from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
1.500
1.5
0.000
0.000

Remark

view all

1.50 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। -- as on 28-Jan-2026

Rating : 77

Forest Case Pending At : 18: Final Approval

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: