Work Profile Report [39W70]

मा0मु0मत्री घोषणा (2008-09 में) सिद्धसौड-टाट-पाली-सिमली मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.सं. 4199/111-2/08 (मु0मं0घो0/08 दिनांक 24.12.08

TS Amount (lakhs) : 110.25 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

110.25

Resanction Cost :

110.25

Tentative Cost :

110.25

Exp. Upto Last Fy :

56.50

For CFY 2024-2025

Remaining :

53.75

Demand :

30.00

Allotment :

0.57

Exp in CFY :

0.57

Total Up to Date Exp :

57.07

Construction Started

Sanction on : 15 years 10 months ago

24 Dec 2008

Physical Progress:

At start of FY 2024-2025 :

70 %

Up to Date :

70 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
1.500
1.5
0.000
0.000

Remark

view all

1.50 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। इससे आगे के भाग में ग्रामीणों द्वारा विवाद किये जाने के कारण मोटर मार्ग का निर्माण नहीं किया गया। -- as on 29-Feb-2024

Rating : 73

Forest Case Pending At : 18: Final Approval

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand