Work Profile Report [39W700]

सुनाउ से बच्छणस्यूं मोटर मार्ग का नव निर्माण (द्वितीय चरण) (वर्ष 2018-19)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिलाधिकारी का पत्र संख्या 334/विविध/2018-19 दिनांक 25.01.2019

TS Amount (lakhs) : 6.3 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

6.30

Resanction Cost :

6.30

Tentative Cost :

6.30

Exp. Upto Last Fy :

2.54

For CFY 2024-2025

Remaining :

3.76

Demand :

3.76

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

2.54

Work completed

Sanction on : 5 years 9 months ago

25 Jan 2019

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
0.5
0.5
0.000
0.5
0.320
0.000

Remark

view all

320 मीटर में ही पहाड कटान कार्य पूर्ण -- as on 25-Apr-2024

Rating : 113

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: