Work Profile Report [39W701]

मून्यापंदेरा से ढामक होते हुए थाला तक मोटर मार्ग (वर्ष 2018-19)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिलाधिकारी का पत्र संख्या 334/विविध/2018-19 दिनांक 25.01.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

20.00

Resanction Cost :

20.00

Tentative Cost :

20.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

20.00

Demand :

0.25

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 5 years 9 months ago

25 Jan 2019

Physical Progress:

At start of FY 2024-2025 :

1 %

Up to Date :

1 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1.5
1.5
0.000
1.5
0.000
0.000

Remark

view all

सर्वे कार्य में ग्रामीणों का विवाद है। -- as on 31-Dec-2020

Rating : 1

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand