Administrative Approval Detail : शासनादेश संख्या 6551/।।।(2)/21-08(एमएलए)/2017 टीसी-। दिनांक 29.12.2021
TS Amount (lakhs) : 3.83 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
65.03
Resanction Cost :
65.03
Tentative Cost :
65.03
Exp. Upto Last Fy :
0.50
For CFY 2025-2026
Remaining :
64.53
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.50
Unstarted Work
Sanction on : 4 years 4 days ago
29 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 2 years 2 months from now
31 Mar 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों से समरेखण हेतु विकल्प मांगे गये हैं। -- as on 02-Jan-2026