Work Profile Report [39W826]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 10(1)/।।।(2)/21-08(एमएलए)/2017 टीसी-चार दिनांक 03.01.2022
TS Amount (lakhs) : 7.43 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.95
Resanction Cost :
72.95
Tentative Cost :
72.95
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
72.95
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Unstarted Work
Sanction on : 4 years 2 weeks ago
03 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 2 years 2 months from now
31 Mar 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण में ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: