Work Profile Report [39W886]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/108221/2023 ई-फाईल सं0 333996 /लोक निर्माण अनुभाग-2 दिनांक 21.03.2023
TS Amount (lakhs) : 84.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.20
Resanction Cost :
84.20
Tentative Cost :
84.20
Exp. Upto Last Fy :
23.22
For CFY 2024-2025
Remaining :
60.98
Demand :
40.00
Allotment :
37.63
Exp in CFY :
37.63
Total Up to Date Exp :
60.85
Work completed
Sanction on : 1 year 8 months ago
21 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.40 िकमी0 में पहाड कटान कार्य पूर्ण। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: