Work Profile Report [3W2]

वल्मरा स्याल्दे केदार मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : 1437/।।।(2)/16-15(प्रा0आ0)/2004 दिनांक 21.03.2016

TS Amount (lakhs) : 1960.75 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

208.50

Resanction Cost :

1073.13

Tentative Cost :

1047.83

Saving

25.30

Exp. Upto Last Fy :

809.24

For CFY 2024-2025

Remaining :

263.89

Demand :

20.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

809.24

Work completed

Sanction on : 8 years 4 months ago

21 Mar 2016

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 3 years 4 months ago

31 Mar 2021

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
15
15
15
-

Remark

view all

Overall Saving 25.3 has been recorded as expected cost of work reduced from 1073.13 to 1047.83 .
कार्य की कुल अवशेष धनराशि रू0 263.89 लाख है जिसमें रू0 238.59 लाख का मुआवजा वितरण किया जाना है।
-- as on 20-Jul-2024

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand