Work Profile Report [3W2]

वल्मरा स्याल्दे केदार मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1437/।।।(2)/16-15(प्रा0आ0)/2004 दिनांक 21.03.2016

TS Amount (lakhs) : 1960.75 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

208.50

Resanction Cost :

1073.13

Tentative Cost :

959.24

Saving

113.89

Exp. Upto Last Fy :

809.24

For CFY 2025-2026

Remaining :

263.89

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

809.24

Work completed

Sanction on : 9 years 9 months ago

21 Mar 2016

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 years 9 months ago

31 Mar 2021

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
15
15
15
-

Remark

view all

कार्य की कुल अवशेष धनराशि रू0 263.89 लाख है जिसमें रू0 113.89 लाख बचत है। अवशेष धनराशि रू0 150.00 लाख का मुआवजा वितरण किया जाना है। जिसके अन्तर्गत मुआवजा प्रस्ताव गठन की कार्यवाही गतिमान है। -- as on 30-Dec-2025

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: