Work Profile Report [3W237]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.स. 4997/।।र्।)।।-31(प्रा.आ.)/2011 दि. 19 सितम्बर, 2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
78.12
Resanction Cost :
78.12
Tentative Cost :
57.01
Saving
21.11
Exp. Upto Last Fy :
7.01
For CFY 2025-2026
Remaining :
71.11
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.01
Alignment Approved
Sanction on : 14 years 4 months ago
19 Sep 2011
Physical Progress:
At start of FY 2025-2026 :
76 %
Up to Date :
76 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नापभूमि प्रतिकर प्रस्ताव गठन की कार्यवाही गतिमान। -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: