Work Profile Report : 3W27

बासोट-घट्टी मोटर मार्ग के किमी. 15 से थापला गांव तक मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 827/111(2)/06-76(प्रा0आ0)/05टी.सी.-01 दि. 28.03.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

142.40

Resanction Cost :

142.40

Tentative Cost :

142.40

Exp. Upto Last Fy :

0.93

For CFY 2025-2026

Remaining :

141.47

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.93

Unstarted Work

Sanction on : 19 years 10 months ago

28 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

15 %

Up to Date :

15 %

Tentative Completion date on : 2 years 1 month from now

31 Mar 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
8
8
8
-

Remark

view all

प्रभागीय वनाधिकारी, अल्मोेड़ा के पत्रांक 3507/12-1(2) दिनांक 03.12.2025 द्वारा प्रमुख वन संरक्षक, नोडल अधिकारी, देहरादून को रिलिस्ट करवाये जाने हेतु पत्र प्रेषित। -- as on 02-Feb-2026

Rating : 15

Forest Case Pending At : 07: Nodal

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: