Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18 | 18 | 18 | 0 |
3W392 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2314/।।।(2)/16-11(प्रा0आ0)/2004
TS Amount (lakhs) : 795.96 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
759.22
Resanction Cost :
759.22
Tentative Cost :
759.22
Exp. Upto Last Fy : 395.68
For CFY 2024-2025
Remaining : 363.54
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 395.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 10 months ago
24 Aug 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
5 years 2 weeks ago
01 Jul 2019
Remark
Bottelneck: no issue
प्रभावित होने वाली नाप भूमि के कृषकों को मुआवजा भुगतान हेतु उचित दस्तावेज कार्यालय में उपलब्ध कराने हेतु खंडिय अमीन एवं कनिष्क अभियंता द्वारा मौखिक रूप से सूचित किया गया है। दस्तावेज उपलब्ध होने के उपरांत मुआवजा वितरण की कार्रवाई की जाएगी। -- as on 13-Jul-2024