Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 1.4 | 0 |
Closed Work 3W462 :
Administrative Approval Detail : 556(ए)/।।।(2)/19-49(एम0एल0ए0)/2017 दि0 01.02.2019
TS Amount (lakhs) : 60.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.58
Resanction Cost :
60.58
Tentative Cost :
60.58
Exp. Upto Last Fy : 45.00
For CFY 2024-2025
Remaining : 15.58
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 45.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
01 Feb 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
3 years 6 months ago
01 Jan 2021
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-Apr-2024