Work Profile Report [3W5]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 2454/111-2/05-07(प्रा0आ0)/05 टी.सी.-1 दि. 28.10.05
TS Amount (lakhs) : 140.53 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
166.80
Resanction Cost :
166.80
Tentative Cost :
161.41
Saving
5.39
Exp. Upto Last Fy :
146.41
For CFY 2024-2025
Remaining :
20.39
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
146.41
Work completed
Sanction on : 18 years 9 months ago
28 Oct 2005
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 2 weeks ago
31 Jul 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 5.39 has been recorded as expected cost of work reduced from 166.8 to 161.41 .
कार्य की कुल अवशेष धनराशि रू0 20.39 लाख है जिसमें रू0 15.00 लाख का मुआवजा वितरण किया जाना है।
-- as on 20-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: