Work Profile Report [3W52]

ताड़ीखेत पीपली सौलाधार चमड़खान गंगोड़ा मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : 288लो0नि0-2/04-15(प्रा0आ0)/04 दि. 27.02.04

TS Amount (lakhs) : 83.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

83.40

Resanction Cost :

83.40

Tentative Cost :

83.40

Exp. Upto Last Fy :

54.54

For CFY 2024-2025

Remaining :

28.86

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

54.54

Construction Started

Sanction on : 20 years 5 months ago

27 Feb 2004

Physical Progress:

At start of FY 2024-2025 :

76 %

Up to Date :

76 %

Tentative Completion date on : 1 year 7 months from now

31 Mar 2026

Actual Completion Date : 3 years 4 months ago

01 Apr 2021

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

कार्य की स्वीकृत लम्बाई 6.00 किमी0 के सापेक्ष स्वीकृत लागत में 2.00 किमी0 लम्बाई में मोटर मार्ग का निर्माण पूर्ण। अवशेष लम्बाई में मोटर मार्ग के निर्माण हेतु पुनरीक्षित आगणन प्रेषित किया गया जिसकी स्वीकृति प्राप्त नही हो पाई। वर्ष 2024-25 में अवशेष धनराशि रू0 28.86 लाख है। अवशेष धनराशि के सापेक्ष रू0 10.00 लाख की धनराशि से निर्मित मार्ग के 2.00 किमी0 लम्बाई में नापभूमि प्रतिकर की कार्यवाही की जा रही है। अवशेष लम्बाई में मार्ग निर्माण हेतु जिला योजना वर्ष 2024-25 के अन्तर्गत रू0 30.00 लाख की योजना स्वीकृत की गयी है। जिला योजना से मार्ग निर्माण के पश्चात् अवशेष धनराशि रू0 18.86 लाख से वित्तीय वर्ष 2025-26 में अग्रिम 4.00 किमी0 लम्बाई में प्रतिकर भुगतान की कार्यवाही की जायेगी। -- as on 22-Jul-2024

Rating : 89

Forest Case Pending At : 21: Final

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand