Work Profile Report [3W52]

ताड़ीखेत पीपली सौलाधार चमड़खान गंगोड़ा मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 288लो0नि0-2/04-15(प्रा0आ0)/04 दि. 27.02.04

TS Amount (lakhs) : 83.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

83.40

Resanction Cost :

83.40

Tentative Cost :

83.40

Exp. Upto Last Fy :

54.54

For CFY 2025-2026

Remaining :

28.86

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

54.54

Construction Started

Sanction on : 21 years 10 months ago

27 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

76 %

Up to Date :

76 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date : 4 years 9 months ago

01 Apr 2021

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

मुआवजा भुगतान हेतु पपत्र तैयार किये जा रहे है। -- as on 31-Dec-2025

Rating : 82

Forest Case Pending At : 21: Final

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand