Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.15 | 7.15 | 7.15 | 0 |
Closed Work 3W522 :
Administrative Approval Detail : शा0सं0 1542/।।।(3)/2020-03(एस0पी0एस0)2020 दिनांक 04.12.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
210.00
Resanction Cost :
210.00
Tentative Cost :
210.00
Exp. Upto Last Fy : 203.35
For CFY 2024-2025
Remaining : 6.65
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 203.35
Work completed
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 100 %
Sanction on :
3 years 7 months ago
04 Dec 2020
Tentative Completion date:
3 years 2 months ago
30 Apr 2021
Actual Completion Date:
3 years 4 months ago
01 Mar 2021
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 31-Mar-2021
Physical Peramenters