Administrative Approval Detail : 4088/।।।(2)/2023-(प्रा0आ0)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
181.86
Resanction Cost :
181.86
Tentative Cost :
181.86
Exp. Upto Last Fy :
144.32
For CFY 2025-2026
Remaining :
37.54
Demand :
0.00
Allotment :
29.39
Exp in CFY :
29.39
Total Up to Date Exp :
173.71
Work completed
Sanction on : 1 year 11 months ago
01 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 27-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: