Work Profile Report [3W76]

तराड़ी डभरा शशिखाल मोटर मार्ग। (मु.म.घोषणा)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents

Administrative Approval Detail : शा.सं. 2404/लो.नि.-2/2003-2 (मु.म.घो.) / 2003 दि0 15.12.2003

TS Amount (lakhs) : 271.55 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

744.20

Resanction Cost :

744.20

Tentative Cost :

744.20

Exp. Upto Last Fy :

50.67

For CFY 2024-2025

Remaining :

693.53

Demand :

50.00

Allotment :

0.00

Exp in CFY :

6.93

Total Up to Date Exp :

57.60

Construction Started

Sanction on : 20 years 8 months ago

15 Dec 2003

Physical Progress:

At start of FY 2024-2025 :

10 %

Up to Date :

10 %

Tentative Completion date on : 1 year 7 months from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
40
21.8
0.000
21.8
0.000
0.000
Bridge
1
1
0 (0.000m)
1
0 (0.000m)
0 (0.000m)

Remark

view all

दिनांक 03.08.2024 को ग्राम बन्द्राण बसनाल की 9.81है0 सिविल भूमि का स्थल निरीक्षण करने पर वृक्षारोपण हेतु भूमि उपयुक्त पाई गयी। इस कार्यालय के पत्रांक 1699/36सी दि0 06.08.2024 द्वारा सैद्वान्तिक स्वीकृति के शर्तो के अनुपालन आख्या प्रेषित करने के लिए उचित दिशा निर्देश दिये जाने हेतु प्रभागीय वनाधिकारी अल्मोड़ा को पत्र प्रेषित। -- as on 12-Aug-2024

Rating : 12

Forest Case Pending At : 12: AIP DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand