Work Profile

गगास उड़ी महादेव सेलापानी भिकियासैंण मरचुला मोटर मार्ग।


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Badhangar Gadhera

Administrative Approval Detail : शा.सं. 288लो.नि.-2/01-15(प्रा.आ.)/04 दि. 27.02.04

TS Amount (lakhs) : 511.31 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

556.00

Resanction Cost :

556.00

Tentative Cost :

556.00

Exp. Upto Last Fy : 556.00

For CFY 2024-2025

Remaining : 0.00

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 556.00

Work completed

Physical Progress:

At start of FY 2024-2025 : 76 %

Up to Date : 100 %

Sanction on :
20 years 4 months ago
27 Feb 2004


Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024


Actual Completion Date:
1 year 1 week ago
06 Jul 2023


Rating : 102

Remark

Forest Status 21: Final

Bottelneck: no issue


कार्य पूर्ण। -- as on 16-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 40 12 12 0
Currently only Bank Gaurantee information is avilable