Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 40 | 12 | 12 | 0 |
Closed Work 3W81 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Badhangar Gadhera
Administrative Approval Detail : शा.सं. 288लो.नि.-2/01-15(प्रा.आ.)/04 दि. 27.02.04
TS Amount (lakhs) : 511.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
556.00
Resanction Cost :
556.00
Tentative Cost :
556.00
Exp. Upto Last Fy : 556.00
For CFY 2024-2025
Remaining : 0.00
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 556.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
20 years 4 months ago
27 Feb 2004
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 year 1 week ago
06 Jul 2023
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-Apr-2024
Physical Peramenters