Work Profile Report [3W815]
Tenders
Project Activities
alerts
Administrative Approval Detail : E Finle No 56049
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.98
Resanction Cost :
243.98
Tentative Cost :
243.98
Exp. Upto Last Fy :
94.32
For CFY 2025-2026
Remaining :
149.66
Demand :
140.00
Allotment :
100.00
Exp in CFY :
62.04
Total Up to Date Exp :
156.35
Construction Started
Sanction on : 9 months 1 week ago
19 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
85 %
Tentative Completion date on : 2 days 1 hour from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इण्टर कोट , टापकोट एवं पी सी का कार्य पूर्ण । अवशेष कार्य प्रगति में है। -- as on 27-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: