Work Profile Report [3W816]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E Finle No 64221
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
468.88
Resanction Cost :
468.88
Tentative Cost :
468.88
Exp. Upto Last Fy :
90.95
For CFY 2025-2026
Remaining :
377.93
Demand :
275.00
Allotment :
100.00
Exp in CFY :
62.26
Total Up to Date Exp :
153.21
Construction Started
Sanction on : 8 months 3 weeks ago
22 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
50 %
Tentative Completion date on : 3 months 1 week from now
28 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग, इण्टर एव 3.00 किमी. लम्बाई में टाॅप कोट का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: