Work Profile Report [3W821]

जनपद अल्मोड़ा में विधानसभा क्षेत्र रानीखेत में चमड़खान कनौली सैलापानी मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E File No 68299/2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

63.04

Resanction Cost :

63.04

Tentative Cost :

63.04

Exp. Upto Last Fy :

0.10

For CFY 2025-2026

Remaining :

62.94

Demand :

40.00

Allotment :

25.00

Exp in CFY :

22.21

Total Up to Date Exp :

22.31

Construction Started

Sanction on : 8 months 1 week ago

25 Feb 2025

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

60 %

Tentative Completion date on : 4 months 6 hours from now

04 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
3.000
0.000

Remark

view all

2 किलोमीटर लंबाई में पहाड़ काटने का कार्य पूर्ण अवशेष कार्य प्रगति पर -- as on 09-Oct-2025

Rating : 56

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: