Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
3W92 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2454/111-2/05-07(प्रा.आ.)/05 टी.सी.-। दि. 28.10.05
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
82.56
Resanction Cost :
82.56
Tentative Cost :
82.56
Exp. Upto Last Fy : 2.07
For CFY 2024-2025
Remaining : 80.49
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.07
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 06: Conservator
Bottelneck: Long Term Forest Approval
इस कार्यालय के पत्र 1065/36सी. दिनांक 21.05.2024 द्वारा सही के0एम0एल0 फाईल आँन लाईन कर प्र्रभागीय वनाधिकारी, अल्मोड़ा को अग्रिम आवश्यक कार्यवाही हेतु पत्र प्रेषित। -- as on 28-May-2024
Physical Peramenters