Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
3W92 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2454/111-2/05-07(प्रा.आ.)/05 टी.सी.-। दि. 28.10.05
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 82.56 Lacs
Resanction Cost : 82.56 Lacs
Exp. Upto Last Fy : 2.07 Lacs
For CFY 2024-2025
Remaining : 80.49 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.07 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
18 years 6 months ago
28 Oct 2005
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: Long Term Forest Approval
पुनः इस कार्यालय के पत्रांक 899/36सी. दिनांक 27.04.2024 द्वारा निरीक्षण आख्या उपलब्ध कराने हेतु पत्र प्रेषित। निरीक्षण आख्या अपेक्षित। -- as on 27-Apr-2024
Physical Peramenters