Work Profile Report [3W96]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा.सं. 2454/111-2/05-07(प्रा.आ.)/05 टी.सी.-। दि. 28.10.05
TS Amount (lakhs) : 83.4 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
83.40
Resanction Cost :
83.40
Tentative Cost :
65.88
Saving
17.52
Exp. Upto Last Fy :
56.32
For CFY 2025-2026
Remaining :
27.08
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
56.32
Work deferred
Sanction on : 20 years 2 months ago
28 Oct 2005
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
45 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date : 3 years 9 months ago
01 Apr 2022
Physical Linear Components
Remark
पुनः क्षतिपूरक वृक्षारोपण स्थल का कब्जा दिनांक 14.11.2025 को वन क्षेत्राधिकारी, जौरासी को दिया गया है। -- as on 14-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: