Work Profile Report [3W99]

जनपद अल्मोड़ा में सरपटा चनुली कोटा बासोट मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा.सं. 2491/111(2)/06-36 (प्रा.आ.)/06 दि. 19.07.06

TS Amount (lakhs) : 160.2 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

160.20

Resanction Cost :

160.20

Tentative Cost :

128.39

Saving

31.81

Exp. Upto Last Fy :

108.59

For CFY 2025-2026

Remaining :

51.61

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

108.59

Construction Started

Sanction on : 19 years 6 months ago

19 Jul 2006

Physical Progress:

At start of FY 2025-2026 :

76 %

Up to Date :

76 %

Tentative Completion date on : 2 years 2 months from now

31 Mar 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
9
6.32
6.32
-

Remark

view all

6.32 किमी0 लम्बाई के सापेक्ष 4.00 किमी0 लम्बाई में मार्ग का निर्माण कार्य स्वीकृत धनराशि के अन्तर्गत करा लिया गया है। अवशेष लम्बाई का पुनरीक्षित आगणन प्रेषित किया जा रहा है। वर्तमान में 4.00 किमी0 लम्बाई में डामरीकरण का कार्य पी0एम0जी0एस0वाई0 द्वारा प्रस्तावित किया गया है। -- as on 02-Jan-2026

Rating : 76

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: