Work Profile Report [40W158]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा॰सं॰ 532/जिला योजना /अर्थ एवं संख्या /लो॰नि॰वि॰/2012-13 दिनांक 11-9-2012
TS Amount (lakhs) : 12.6 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy :
7.18
For CFY 2024-2025
Remaining :
5.42
Demand :
5.42
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.18
Unstarted Work
Sanction on : 12 years 3 months ago
11 Sep 2012
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
उत्तराखण्ड शासन के पत्र सं॰ 189 /एक्श-4-17/1(266)/2016 दि॰ 01-09-2017 द्वारा विधिवत् स्वीकृति प्राप्त। अग्रिम कार्यवाही गतिमान है। -- as on 23-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: