Work Profile Report [40W17]

fत्रयुगीनारायण- तोषी मोटर मार्ग नव fनर्माण सेतु सfहत।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2555/।।।-2/06-41 (प्रा॰आ॰)/06 दि0 26.09.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

148.80

Resanction Cost :

451.79

Tentative Cost :

451.79

Exp. Upto Last Fy :

154.42

For CFY 2024-2025

Remaining :

297.37

Demand :

131.78

Allotment :

93.00

Exp in CFY :

56.08

Total Up to Date Exp :

210.50

Construction Started

Sanction on : 18 years 1 month ago

26 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

33 %

Up to Date :

40 %

Tentative Completion date on : 4 months 3 weeks from now

15 Apr 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
0.000
6
0.000
0.000
Bridge
1 (25m)
1 (25m)
0 (0.000m)
1 (25m)
0 (0.000m)
0 (0.000m)

Remark

view all

स्वीकृति लम्बाई में 2.00 कि॰मी॰ लं॰ में पहाड कटान कार्य पूर्ण। कि॰मी॰ 3 में कार्य प्रगति पर। -- as on 04-Nov-2024

Rating : 49

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand