Work Profile Report [40W23]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 764/।।।(2)/08-65 (प्रा॰आ॰)/07 दिनांक 24.3.2008
TS Amount (lakhs) : 16.19 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
240.83
Resanction Cost :
240.83
Tentative Cost :
240.83
Exp. Upto Last Fy :
42.63
For CFY 2024-2025
Remaining :
198.20
Demand :
151.28
Allotment :
70.37
Exp in CFY :
56.37
Total Up to Date Exp :
99.00
Construction Started
Sanction on : 16 years 7 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
30 %
Tentative Completion date on : 5 months 3 weeks from now
17 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सेतु के एवटमेन्ट का कार्य प्रगति पर। -- as on 22-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: