Work Profile Report [40W383]

नैणी-गौण्डार (पौण्डार) मोटर मार्ग का डामरीकरण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : fजलाfधकारी, रुद्रप्रयाग का पत्रांक 454/fजला योजना/अर्थ एवं संख्या /लो॰fन॰fव॰ /2017-18 fदनांक 08-11-2017

TS Amount (lakhs) : 20 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

20.00

Resanction Cost :

20.00

Tentative Cost :

20.00

Exp. Upto Last Fy :

17.40

For CFY 2024-2025

Remaining :

2.60

Demand :

2.60

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

17.40

Work completed

Sanction on : 7 years 1 month ago

08 Nov 2017

Physical Progress:

At start of FY 2024-2025 :

65 %

Up to Date :

65 %

Tentative Completion date on : 5 years 8 months ago

31 Mar 2019

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
0.58
0.27
0.27
-

Remark

view all

कार्य पूर्ण। दायित्व शेष। -- as on 30-Sep-2020

Rating : 87

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: