Work Profile Report [40W469]

रांऊलैंक जग्गीबगवान मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी, रुद्रप्रयाग का पत्रांक 508/जि॰यो॰-03/2022 दिनंाक 09-09-2022

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5.00

Resanction Cost :

5.00

Tentative Cost :

5.00

Exp. Upto Last Fy :

1.00

For CFY 2024-2025

Remaining :

4.00

Demand :

4.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.00

none

Sanction on : 2 years 3 months ago

09 Sep 2022

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य प्रगति पर। -- as on 24-Apr-2023

Rating : 20

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand