Work Profile Report [40W492]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा॰सं॰ 28022-0465/2023 दिनंाक 28.03.202
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.29
Resanction Cost :
79.29
Tentative Cost :
79.29
Exp. Upto Last Fy :
43.01
For CFY 2024-2025
Remaining :
36.28
Demand :
15.90
Allotment :
14.00
Exp in CFY :
2.90
Total Up to Date Exp :
45.91
Construction Started
Sanction on : 1 year 4 months ago
28 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
45 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान कार्य प्रगति पर। -- as on 22-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: