Work Profile Report [40W544]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा॰सं॰ 168831/2023 इ-फाइल सं॰ 48456 लोक निर्माण अनुभाग-2 दिनांक 15-10-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.53
Resanction Cost :
121.53
Tentative Cost :
121.53
Exp. Upto Last Fy :
6.03
For CFY 2024-2025
Remaining :
115.50
Demand :
115.50
Allotment :
86.00
Exp in CFY :
75.09
Total Up to Date Exp :
81.12
Work completed
Sanction on : 1 year 1 month ago
15 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 day ago
22 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 04-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand