Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.12 | 4.12 | 0.000 | 4.12 | 0.000 | 0.000 |
40W544 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 168831/2023 इ-फाइल सं॰ 48456 लोक निर्माण अनुभाग-2 दिनांक 15-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
121.53
Resanction Cost :
121.53
Tentative Cost :
121.53
Exp. Upto Last Fy : 6.03
For CFY 2024-2025
Remaining : 115.50
Demand : 115.50
Allotment : 1.00
Exp in CFY : 0.67
Total Up to Date Exp : 6.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 100 %
Sanction on :
9 months 2 days ago
15 Oct 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण, नाली निर्माण, स्कपर निर्माण एवं पी॰सी॰ कार्य पूर्ण। दायित्व शेष। -- as on 28-Jun-2024
Physical Peramenters