Work Profile Report [40W588]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासन, देहरादून के शासनादेश ई-पत्रावली सं॰ 77465, दिनंाक 20-09-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
159.20
Resanction Cost :
159.20
Tentative Cost :
159.20
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
159.20
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 3 months 5 days ago
20 Sep 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 07-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand