Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 15.000 | 0 | 0.000 | 0.000 |
43W1029 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन का पत्रांक 5082/111(2)2023-01(प्रा0आ0)/2023 दि0 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
213.52
Resanction Cost :
213.52
Tentative Cost :
213.52
Exp. Upto Last Fy : 179.30
For CFY 2024-2025
Remaining : 34.22
Demand : 34.22
Allotment : 179.30
Exp in CFY : 0.00
Total Up to Date Exp : 179.30
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
4 months 3 weeks ago
25 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Apr-2024