Work Profile Report [43W1037]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file 51381/13 dt 01-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
126.19
Resanction Cost :
126.19
Tentative Cost :
126.19
Exp. Upto Last Fy :
3.52
For CFY 2024-2025
Remaining :
122.67
Demand :
45.00
Allotment :
50.00
Exp in CFY :
34.93
Total Up to Date Exp :
38.45
Construction Started
Sanction on : 10 months 4 days ago
19 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
25 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 1 तक पहाड कटान कार्य पूर्ण, किमी0 2 में कोर्ट से स्टे होने के कारण कार्य रूका है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: