Work Profile Report [43W1069]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : e file 24396 dt 04-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.61
Resanction Cost :
89.61
Tentative Cost :
89.61
Exp. Upto Last Fy :
21.14
For CFY 2025-2026
Remaining :
68.47
Demand :
65.00
Allotment :
65.00
Exp in CFY :
48.66
Total Up to Date Exp :
69.80
Construction Started
Sanction on : 1 year 2 months ago
04 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
65 %
Tentative Completion date on : 2 months 1 week from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी1,जी2,जी3 का कार्य पूर्ण, अवशेष कार्य प्रगति पर । -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: