Work Profile Report [43W1078]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : e file 51381 dt 02-01-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
191.48
Resanction Cost :
191.48
Tentative Cost :
191.48
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
191.38
Demand :
165.00
Allotment :
165.00
Exp in CFY :
54.70
Total Up to Date Exp :
54.80
Construction Started
Sanction on : 1 year 3 weeks ago
02 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
75 %
Tentative Completion date on : 3 months 13 hours from now
24 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
G1, G2 का कार्य पूर्ण । अवशेष कार्य प्रगति पर है । G3 का कार्य प्रगति में है, 25.01.2026 G3 का कार्य पूर्ण कर लिया जायेगा। -- as on 20-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand