Administrative Approval Detail : e file 74390 dt 19-12-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
191.52
Resanction Cost :
191.52
Tentative Cost :
140.00
Saving
51.52
Exp. Upto Last Fy :
2.96
For CFY 2025-2026
Remaining :
188.56
Demand :
95.00
Allotment :
100.00
Exp in CFY :
68.05
Total Up to Date Exp :
71.01
Construction Started
Sanction on : 1 year 1 month ago
18 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
75 %
Tentative Completion date on : 5 months 6 days from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। -- as on 03-Jan-2026