Work Profile Report [43W1081]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file 51399/13 dt 30-04-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
208.06
Resanction Cost :
208.06
Tentative Cost :
208.06
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
208.06
Demand :
88.00
Allotment :
100.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 7 months 2 weeks ago
30 Apr 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
5 %
Tentative Completion date on : 6 months 1 week from now
29 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 01 व 02 में दीवार निर्माण कार्य प्रगति पर। -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: