Administrative Approval Detail : e file 51399/13 dt 30-04-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
208.06
Resanction Cost :
208.06
Tentative Cost :
208.06
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
208.06
Demand :
88.00
Allotment :
150.00
Exp in CFY :
35.60
Total Up to Date Exp :
35.60
Construction Started
Sanction on : 8 months 3 weeks ago
30 Apr 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
20 %
Tentative Completion date on : 5 months 5 days from now
29 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी 01 व 02 में जी1 एकत्रीकरण कार्य प्रगति में । -- as on 31-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: