Work Profile Report [43W1082]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E File No 37809/12 dt 01/09/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.80
Resanction Cost :
30.80
Tentative Cost :
30.80
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
30.80
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 4 months 1 day ago
01 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
10 %
Tentative Completion date on : 2 months 4 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work started -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: