Work Profile Report [43W214]

जनपद टिहरी गढ़वाल के प्रतापनगर में ननवा से थात मुंशांकरी तक मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 5527/।।।(2)/10-04 (एम0एल0ए0)/2010 दि0 13/12/10

TS Amount (lakhs) : 75.6 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

75.60

Resanction Cost :

75.60

Tentative Cost :

75.60

Exp. Upto Last Fy :

49.10

For CFY 2024-2025

Remaining :

26.50

Demand :

10.00

Allotment :

0.00

Exp in CFY :

3.70

Total Up to Date Exp :

52.79

Construction Started

Sanction on : 13 years 11 months ago

13 Dec 2010

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
0.000
6
0.000
0.000

Remark

view all

प्रतिकर वितरण कार्य प्रगति पर है । -- as on 16-May-2024

Rating : 73

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand