Work Profile Report [43W231]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 4331/111(2)/12-08(मु0मं0घो0)/2012 दि0 26.10.12
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
251.60
Resanction Cost :
251.60
Tentative Cost :
251.60
Exp. Upto Last Fy :
197.22
For CFY 2025-2026
Remaining :
54.38
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
197.22
Phase1 DPR Submitted
Sanction on : 12 years 8 months ago
26 Oct 2012
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 3 months 2 weeks from now
30 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर वितरण का कार्य प्रगति पर है । -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: