Work Profile Report [43W237]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 213/111(2)/13-08(मु0मा0घो0)/2012 दि0 14.01.2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
62.90
Resanction Cost :
62.90
Tentative Cost :
62.90
Exp. Upto Last Fy :
58.29
For CFY 2024-2025
Remaining :
4.61
Demand :
4.61
Allotment :
0.00
Exp in CFY :
0.89
Total Up to Date Exp :
59.18
Construction Started
Sanction on : 11 years 10 months ago
14 Jan 2013
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग पर स्वीकृत प्रतिकर आंवटित कर दिया गया है अवशेष प्रतिकर पत्रावली गठित की जा रही है । -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand