Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 3.500 | 1.5 | 1.500 | 0.000 |
43W25 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2454/111(2)/05-07(प्रा0आ0)/05 टी0सी0 दि0 28.10.05 एवं शा0 सं0 3004/111 (2)/16-07(प्रा0आ0)/2005 टी0सी0-1 दि0 21.11.2016
TS Amount (lakhs) : 247.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
69.50
Resanction Cost :
259.73
Tentative Cost :
259.73
Exp. Upto Last Fy : 62.21
For CFY 2024-2025
Remaining : 197.52
Demand : 100.00
Allotment : 0.00
Exp in CFY : 12.47
Total Up to Date Exp : 74.67
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पूर्व में ग्रामीणांे द्वारा विवाद गया । प्रतिकर विवाद सुलझा दिया गया है कार्य प्रगति पर -- as on 09-May-2024
Physical Peramenters