Work Profile Report [43W28]

खोला से अगरोड़ा डिग्री कालेज मो0 मार्ग का नवनिर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेन संख्या - 2503/111-2/06 -37(प्रा0आ0)/06 दिनांक 20.06.2006

TS Amount (lakhs) : 57 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

81.00

Resanction Cost :

81.00

Tentative Cost :

81.00

Exp. Upto Last Fy :

26.33

For CFY 2024-2025

Remaining :

54.67

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

26.33

Construction Started

Sanction on : 18 years 1 month ago

20 Jun 2006

Physical Progress:

At start of FY 2024-2025 :

40 %

Up to Date :

62 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
3.12
1.250
1.87
0.400
0.000

Remark

view all

1.25 किमी0 में पहाड कटान पूर्व मे पूर्ण ।अवशेष भाग में ग्राम पंचायत बंगद्वारा की भूमि पड रही है जिसमें ग्रामवासियों द्वारा सडक निर्माण हेतु भूमि नही दी जा रही है आम सहमति हेतु सहा0 अभि0 156/1 सी दि0 24.06.24 को प्रेषित एवं दि0 28.06.24 की बैठक में ग्रामीणों द्वारा पुनः अनापत्ति पत्र प्रेषित किया गया है । -- as on 05-Aug-2024

Rating : 66

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: