Work Profile Report [43W323]

जनपद टिहरी के विधानसभा प्रतापनगर में कोरदी से बुरांशखण्डा तक सड़क निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 1152/111(2)/14-62 (प्रा0आ0)/2013 दि0 21.02.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

51.03

Resanction Cost :

51.03

Tentative Cost :

51.03

Exp. Upto Last Fy :

0.23

For CFY 2024-2025

Remaining :

50.80

Demand :

20.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.23

Survey work done

Sanction on : 10 years 10 months ago

21 Feb 2014

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

10 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
5
-

Remark

view all

पूर्व में मार्ग पर समरेखण विवाद था। सहायक अभियन्ता द्वारा माह जनवरी 2024 में कास्तकारों के साथ बैठक की गयी, जिसमें कास्तकारों द्वारा समरेखण निर्धारण हेतु सहमति दी गयी वर्तमान में मार्ग पर सर्वेक्षण कार्य पूर्ण कर दिया गया है । भू वैज्ञानिक निरीक्षण किया जा चुका है । आख्या प्राप्त । समरेखण गठन की कार्यवाही गतिमान है । -- as on 24-Oct-2024

Rating : 11

No Forest Case in The Work

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand