Work Profile Report [43W447]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 2997/111(2)15-06(मु0मं0घो0)/2015 दि0 08.05.2015
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.97
Resanction Cost :
32.97
Tentative Cost :
32.97
Exp. Upto Last Fy :
6.67
For CFY 2024-2025
Remaining :
26.30
Demand :
12.00
Allotment :
11.44
Exp in CFY :
11.44
Total Up to Date Exp :
18.11
Alignment Approved
Sanction on : 9 years 7 months ago
08 May 2015
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 1 month 4 weeks from now
25 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.50 किमी0 लम्बाई मार्ग का समरेखण स्वीकृत। डी0पी0आर0 गठन की कार्यवाही गतिमान है। -- as on 15-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: