Work Profile Report [43W711]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : ष्शा0 सं0 2387/111(2)/ 16-09(एम0एल0ए0) /2015 दि0 01.09.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
11.37
Resanction Cost :
11.37
Tentative Cost :
11.37
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
11.37
Demand :
5.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 9 years 4 months ago
01 Sep 2016
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 5 months 3 weeks from now
30 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
A letter has been sent to the Gram Pradhan to convene a meeting vide letter No 18/01C dt 30.12.2025 -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: