Work Profile Report [43W726]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 1256/111(2)/19-13(एम0एल0ए0)/ 2017 दि0 07.03.2019
TS Amount (lakhs) : 140.24 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.24
Resanction Cost :
140.24
Tentative Cost :
140.24
Exp. Upto Last Fy :
128.88
For CFY 2024-2025
Remaining :
11.36
Demand :
11.00
Allotment :
11.36
Exp in CFY :
3.01
Total Up to Date Exp :
131.89
Work completed
Sanction on : 5 years 9 months ago
07 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date : 2 months 3 weeks ago
01 Oct 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 09-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand