Administrative Approval Detail : शा0 सं0 1256/111(2)/19-13(एम0एल0ए0)/ 2017 दि0 07.03.2019
TS Amount (lakhs) : 140.24 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.24
Resanction Cost :
140.24
Tentative Cost :
140.24
Exp. Upto Last Fy :
128.88
For CFY 2024-2025
Remaining :
11.36
Demand :
7.00
Allotment :
0.00
Exp in CFY :
2.88
Total Up to Date Exp :
131.75
In Maintenance After Completion
Sanction on : 5 years 8 months ago
07 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date : 4 years 7 months ago
01 Apr 2020
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 09-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: