Work Profile Report [43W749]

जनपद टिहरी गढ़वाल में सौन्ध गाढ से चाका सिलोडा तक मोटर मार्ग नव निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 409/111(2)/19-12(एम0एल0ए0)/ 2017 दि0 29.01.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

18.54

Resanction Cost :

18.54

Tentative Cost :

18.54

Exp. Upto Last Fy :

1.50

For CFY 2025-2026

Remaining :

17.04

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.50

Survey work done

Sanction on : 6 years 11 months ago

29 Jan 2019

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

20 %

Tentative Completion date on : 1 year 4 months from now

31 May 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

पी0एम0जी0एस0वाई-4 के अन्तर्गत प्रस्तावित है। -- as on 31-Dec-2025

Rating : 33

Forest Case Pending At : 02: Division

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: