Work Profile Report [43W749]

जनपद टिहरी गढ़वाल में सौन्ध गाढ से चाका सिलोडा तक मोटर मार्ग नव निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 409/111(2)/19-12(एम0एल0ए0)/ 2017 दि0 29.01.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

18.54

Resanction Cost :

18.54

Tentative Cost :

18.54

Exp. Upto Last Fy :

1.50

For CFY 2024-2025

Remaining :

17.04

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.50

Alignment Approved

Sanction on : 5 years 10 months ago

29 Jan 2019

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

20 %

Tentative Completion date on : 2 years 3 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

आपत्तियों का निराकरण किया जा रहा है । इस कार्यालय के पत्रांक 3540/23सी दि0 07.12.2024 द्वारा पुनः क्षतिपूरक वृक्षारोपण भूमि हेतु जिलाधिकारी टिहरी गढ़वाल को पत्र लिखा गया है । -- as on 09-Dec-2024

Rating : 38

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: