Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
43W749 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 409/111(2)/19-12(एम0एल0ए0)/ 2017 दि0 29.01.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 18.54 Lacs
Resanction Cost : 18.54 Lacs
Exp. Upto Last Fy : 1.50 Lacs
For CFY 2024-2025
Remaining : 17.04 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.50 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 3 months ago
29 Jan 2019
Tentative Completion date:
4 years 1 month ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Long Term Forest Approval
इस मार्ग का समरेखण अधीक्षण अभियन्ता, 8 वां वृत, लो0नि0वि0 नई टिहरी के पत्रांक 2876/740सी-8/2021 दि0 10.06.2021 द्वारा स्वीकृत हुआ, मार्ग पर ग्राम सौन्धगाढ एवं ग्राम सिलोडा का समरेखण सम्बन्धित विवाद रहा। विवाद सुलझाने के बाद मार्ग पर दि0 15.06.2022 को पेडो की गिनती हेतु सयुंक्त निरीक्षण हुआ, तत्पश्चात क्षतिपूरक वृक्षारोपण, जियो रिफरेन्स मैप, टोपोग्राफी मैप एवं हवाई दूरी प्रमाण पत्र वन विभाग मुख्यालय से प्राप्त किये गये। वर्तमान में वनभूमि पत्रावली गठित की जा चुकी है वर्तमान में जिलाधिकारी महोदय के स्तर पर लम्बित है । -- as on 27-Apr-2024
Physical Peramenters