Work Profile Report [43W754]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0 सं0 3191/111(2)/19-13 (प्रा0आ0)/2018 दि0 21.08.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.55
Resanction Cost :
47.55
Tentative Cost :
47.55
Exp. Upto Last Fy :
0.56
For CFY 2024-2025
Remaining :
46.99
Demand :
15.00
Allotment :
0.00
Exp in CFY :
2.30
Total Up to Date Exp :
2.86
Alignment Approved
Sanction on : 4 years 11 months ago
21 Aug 2019
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर वितरण प्रगति पर । -- as on 15-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: