Work Profile Report [43W891]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0 सं0 24396 दि0 17.10.2022
TS Amount (lakhs) : 203.21 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
203.21
Resanction Cost :
203.21
Tentative Cost :
203.21
Exp. Upto Last Fy :
185.06
For CFY 2024-2025
Remaining :
18.15
Demand :
12.00
Allotment :
0.00
Exp in CFY :
0.44
Total Up to Date Exp :
185.50
Work completed
Sanction on : 1 year 9 months ago
17 Oct 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 4 weeks ago
17 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 10-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: